Decision details
Determination for Sandringham Court section 38/278/228 agreement
Decision Maker: Director of City Development, Director of Transport, Environment and Planning
Decision status: Decision Made
Is Key decision?: No
Is subject to call in?: No
Decision:
Background / Decision Summary:
City of York Council entered into an agreement with York (Haxby
Road) Limited, the developers of Sandringham Court (off White Cross
Road, Guildhall Ward), in 2013. The purpose of the agreement, under
Sections 38, 228 and 278 of the Highways Act 1980, was to enable
the construction of the development’s access road to an
adoptable standard so that the road would become maintainable at
public expense by the Council.
A cash bond of £40,000 was agreed as part of the agreement
and is held by CYC. The current value inclusive of interest is
£44,990.69
York (Haxby Road) Limited went into administration and was
liquidated. The agreement was novated to Niche Homes Limited in
2014.
A part 1 certificate was issued by the Council certifying that the
highway infrastructure works were completed to the satisfaction of
the Council in 2013.
For the road adoption process to progress further, the Council
requires confirmation that the drainage/sewage apparatus has been
adopted by the relevant body (Yorkshire Water in this case).
Unfortunately, the drainage adoption did not progress as planned. A
section 104 agreement is in place with Yorkshire Water for the
surface water sewers (although the adoption process is not
complete), but there is no agreement in place for the foul sewers.
Both sewers therefore remain privately maintained.
Extensive negotiations have taken place between the Council and the
developers, but the developers have confirmed that they are not
willing to undertake the works required for Yorkshire Water to be
able to adopt the sewers.
The value of the cash bond held by the Council is not sufficient to
cover the cost of the works required to complete the adoption
process. This would need to include the works required for the
sewers to be adopted by Yorkshire Water and to complete highway
remedial works. The bond’s value (just under £45,000)
will not cover the full cost of the works (estimated in excess of
£100,000) so the Council would need to make a significant
financial contribution for the works to be completed and would need
to assume the financial and contractual risks associated with the
works. The Council is under no obligation to adopt the road, which
can remain privately maintained, with the responsibility for its
maintenance falling to the landowners.
The Council also needs to consider the issue of street lighting for
the development.
There are currently 4 lamp columns installed in the privately
maintained area. In November 2025, Northern PowerGrid contacted the
residents, advising them that the lamp columns would be
disconnected as the annual equipment inventory had not been
submitted and the electricity is not being paid for.
Officers contacted Northern PowerGrid to ensure that the lights
where not disconnected whilst the issue of road adoption was still
being considered.
A decision is now required on whether the Council should continue
to provide street lighting for the development in the long term
(the estimated cost of electricity and maintenance over the 25-year
lifetime of the 4 lamp columns is £11,300 over 25 years,
equating to £450/year). Legal advice received on this matter
has confirmed that it is not possible for the Council to use the
cash bond to cover the street lighting costs.
The Council’s duty to maintain street lighting (under Section
41 of the Highways Act 1980) applies specifically to adopted
highways. Although the Council cannot be compelled to take the
responsibility for street lighting on a privately maintained
street, the Council is able to make the decision to provide
lighting in this area (under the Public Health Act 1875 & the
Council’s general power of competence). If the Council
decides not to take the responsibility for the streetlights in the
longer term, the responsibility to provide and maintain lighting
will fall back to the landowners.
Decision:
Option 3 - Street to remain privately maintained: The Council could
decide to terminate the agreement, with the street remaining
privately maintainable. The cash bond will need to be paid back to
the developer
Option 5 - Council to assume responsibility for the streetlighting
– recommended option: The Council could decide to assume
responsibility for the 4 lamp columns on the privately maintained
street. This option results in a modest cost for the Council but
would support the Council’s wider objectives (quality of
life, safety, accessibility).
Options Considered:
Highway adoption
1. Adoption without addressing the issues: If the Council were to
adopt Sandringham Court this would not be in accordance with the
adoption process followed by highways authorities (and described in
government guidance here:
https://assets.publishing.service.gov.uk/media/62e7b821d3bf7f75b9121a6a/advice-note-highways-adoption.pdf)
and would result in significant future financial liabilities for
the Council due to the unadopted sewers.
2. Adoption following works carried out by the Council: The Council
could decide to terminate the agreement and use the bond to partly
fund the works required for the sewers and the road to be adopted.
However, the value of the bond will not cover the costs of the
works required for the sewers to be adopted and the Council would
be required to assume significant financial liabilities to bring
the sewers and the road to the required standards.
3. Street to remain privately maintained – recommended
option: The Council could decide to terminate the agreement, with
the street remaining privately maintainable. The cash bond will
need to be paid back to the developer.
Street lighting if the street remains privately maintained
4. Streetlights to remain the responsibility of the landowners: In
line with option 3 above, the Council could decide to refuse to
take the responsibility for street lighting if the street remains
privately maintained. The provision of lighting will fall to the
landowners. If they fail to organise this, it is highly likely that
the streetlights will be disconnected.
5. Council to assume responsibility for the streetlighting –
recommended option: The Council could decide to assume
responsibility for the 4 lamp columns on the privately maintained
street. This option results in a modest cost for the Council but
would support the Council’s wider objectives (quality of
life, safety, accessibility).
Options Rejected:
1. Adoption: unacceptable financial and legal
impact on CYC
2. Adoption following works using the bond: insufficient funds
available to bring the sewers and the road to adoptable
standards.
4. Streetlights to remain the responsibility of the landowners:
although the Council does not have a duty to take the
responsibility for the streetlights, having considered the high
risk of disconnection if the landowners fail to organise and the
modest cost to the Council, this option has been rejected.
Publication date: 10/02/2026
Date of decision: 05/02/2026