Issue - decisions
Active Travel Programme – Project Progress
14/12/2022 - Active Travel Programme – Project Progress
Resolved:
i. Approved Option 1 – Approve the proposed St Georges Field Crossing scheme and scheme delivery arrangements described within this report and presented in Annex A of this document.
Reason: This option achieves the scheme objectives and is affordable within assigned budgets. Timing of the installation will be co-ordinated with the Castle Gateway development. Traffic is predicted to not be
significantly impacted, and the single-stage element of the crossing makes transition from pedestrian crossing to ’Toucan’ crossing achievable.
Resolved:
ii. Approved Option 2 – Approve the proposed Skeldergate scheme and scheme delivery arrangements described within this report and presented in Annex E of this document.
Reason: This option achieves the core aim of the scheme, which is to “improve safety, amenity and accessibility for cyclists on the routealong Skeldergate, and to reduce and/or remove conflict at buildouts”.