Dunnington A166 Church Balk junction improvements
01/12/2009 - Dunnington: A166 Church Balk junction improvements
RESOLVED: i)
That the Executive Member approves for
implementation the scheme shown in Annex A with the
following amendments :-
· traffic islands removed
· red surfacing added inside hatched road markings.
ii)
That Officers be requested to keep the area under observation with
a view to bringing forward proposals for further physical safety
works should this prove to be necessary.
REASON:
To address road safety concerns and deter overtaking manoeuvres on
the A166 at the Church Balk junction in Dunnington. The amendments
respond to consultation feedback on the original
proposals.