Agenda item
Park and Ride: Site Improvements and New Bus Service Contract
To consider a report from the Director of City Development presenting two connected projects for approval. Firstly, a range of infrastructure improvements to five Park and Ride sites to be funded through Bus Service Improvement Plan (BSIP) grant. Secondly, a two-year extension to the contract for the operation of Park and Ride bus services is proposed to enable continuity of service until wider conversations with the York and North Yorkshire Combined Authority (YNYCA) are concluded.
Decision:
Resolved (unanimously):
That Executive
1) Approves £4m of BSIP1 funding and £250k of allocated
YNYCA Bus Grant funding to deliver Park and Ride site improvements as outlined in Annex A.
Reason: To modernise old facilities for existing and future Park
and Ride users and to attract more passengers to use Park and
Ride services.
2) Delegates authority to the Director of City Development (in
consultation with the Director of Governance and the Head of
Procurement) to implement the proposed Park and Ride site
Infrastructure improvements and to carry out any required
procurement processes and to take such steps as are necessary
to procure, award and enter into the resulting contracts.
Reason: To ensure expedient delivery of the projects.
3) Delegates authority to the Director of City Development (in
consultation with the Chief Finance Officer and the Director of
Governance) to explore and implement further income
opportunities associated with Park and Ride including setting
fees for overnight parking.
Reason: To further support the financial viability of Park and Ride
provision.
4) Delegates authority to the Director of City Development (in
consultation with the Director of Governance and the Head of
Procurement) to agree an extension to the existing Park and
Ride contract and any associated leases, of not more than two
years duration, and to take such steps as are necessary to enter
into the resulting variation and extension agreement and lease
extensions.
Reason: To provide continuation of service and to enable the
results of the York and North Yorkshire Combined Authority bus
network review to be incorporated into the new Park and Ride
contract.
Minutes:
The Director of City Development submitted a report which presented two connected projects for approval. Firstly, a range of infrastructure improvements to five Park and Ride sites to be funded through Bus Service Improvement Plan (BSIP) grant. Secondly, a two-year extension to the contract for the operation of Park and Ride bus services was proposed to enable continuity of service until wider conversations with the York and North Yorkshire Combined Authority (YNYCA) were concluded.
The following information was appended to the report:
- Park and Ride site improvements
- Park and Ride site improvement consultation summary
- Equalities Impact Assessment.
The following officers attended for this item:
- Garry Taylor, Director of City Development
- Tom Horner, Head of Transport Policy and Travel
- Behaviour.
The key areas of discussion were:
· The Executive Member reported that it was 35 years since park and ride was formally opened in 1990 with the opening of Askham Bar park and ride. York had the largest park and ride in the UK with nearly 5,000 parking spaces around the outside of the city centre at six different sites. It was one of the most successful in the country with around 3.8 million journeys in 2024.
· Further investment provided an opportunity to improve passenger experience. There had been a positive response to the consultation exercise with over 1,000 people submitting a response. One important development was the creation of integrated transport hubs so that a wide range of people could access different locations. Overnight parking was another strong ask and had been tied in with extended park and ride hours that had already been implemented.
· Ensuring a more accessible offer, which included, changing places, toilets, accessible EV charging and more spacious blue badge parking. It supported a commitment to enabling people to choose sustainable travel options and to reduce congestion in the city centre.
Resolved (unanimously):
That Executive
1) Approves £4m of BSIP1 funding and £250k of allocated
YNYCA Bus Grant funding to deliver Park and Ride site improvements as outlined in Annex A.
Reason: To modernise old facilities for existing and future Park
and Ride users and to attract more passengers to use Park and
Ride services.
2) Delegates authority to the Director of City Development (in
consultation with the Director of Governance and the Head of
Procurement) to implement the proposed Park and Ride site
Infrastructure improvements and to carry out any required
procurement processes and to take such steps as are necessary
to procure, award and enter into the resulting contracts.
Reason: To ensure expedient delivery of the projects.
3) Delegates authority to the Director of City Development (in
consultation with the Chief Finance Officer and the Director of
Governance) to explore and implement further income
opportunities associated with Park and Ride including setting
fees for overnight parking.
Reason: To further support the financial viability of Park and Ride
provision.
4) Delegates authority to the Director of City Development (in
consultation with the Director of Governance and the Head of
Procurement) to agree an extension to the existing Park and
Ride contract and any associated leases, of not more than two
years duration, and to take such steps as are necessary to enter
into the resulting variation and extension agreement and lease
extensions.
Reason: To provide continuation of service and to enable the
results of the York and North Yorkshire Combined Authority bus
network review to be incorporated into the new Park and Ride
contract.
Supporting documents:
-
Item 12 - Park and Ride - Site Improvements and New Bus Service Contract, item 151.
PDF 347 KB View as HTML (151./1) 76 KB -
Item 12 - Park and Ride - Site Improvements and New Bus Service Contract - Annex A, item 151.
PDF 195 KB View as HTML (151./2) 23 KB -
Item 12 - Park and Ride - Site Improvements and New Bus Service Contract - Annex B, item 151.
PDF 1 MB View as HTML (151./3) 28 KB -
Item 12 - Park and Ride - Site Improvements and New Bus Service Contract - Annex C, item 151.
PDF 306 KB View as HTML (151./4) 104 KB