Capital Programme Specification Change Update
Purpose of report: To ensure a consistent
approach and reduce future maintenance costs. Customers will no
longer have the choice of gas fires within their home.
Timescale: The decision is required promptly to apply a consistent
approach for those customers included in the Tenants Choice Scheme
and heating appliance replacement contract.
The results will be almost immediate as the number of gas fires
reduce year by year thereby reducing the number of gas fires to be
serviced and maintained.
Members are asked to: The report will ask members to consider the
removal of gas fires from the current customer choices. Over the
years chimneys currently within our housing stock have been subject
to a number of modifications from that which they were originally
designed. The modifications are such that cannot support new gas
fires without being fully re-lined at a considerable cost. The cost
of re-lining a chimney flue is approximately £1500 plus the
cost of the appliance. The flue lining has an industry standard
lifespan of 15 years which is less than the appliance it is serving
therefore may need replacing again. The electric fire suites are
visually more attractive and are the most popular choice with quite
a large percentage of our customers. A number of customers still
demand gas fires which causes a considerable expense to the
Council, disruption to the customer and future maintenance costs to
the Council.
Decision type: Non-key
Decision status: Decision Made
Wards affected: (All Wards);
Implication: Financial;
Level of Risk: 01-03 Acceptable;
Decision due: 17/03/08 by Executive Member for Health & Adult Social Services
Lead member: Councillor Susan Sunderland cllr.ssunderland@york.gov.uk
Lead director: Director of Housing and Adult Social Services
Department: Housing & Adult Social Services Directorate
Contact: Mark Grandfield, Housing Improvement Manager.
Consultation process
NA
Consultees
NA
Making Representations: In writing or by email to Mark Grandfield by early March
Decisions
- 18/03/2008 - Housing Capital Programme Specification Change
Agenda items
- 17/03/2008 - Executive Member for Housing and Adult Social Services Advisory Panel Housing Capital Programme Specification Change 17/03/2008
Documents
- Committee Report for Choice of Fires in Customers Houses