Issue - decisions
Capital Budget 2024/25 to 2028/29
26/01/2024 - Capital Budget 2024/25 to 2028/29
Recommended:
i. That Council agree to the revised capital programme of £395.186m that reflects a net overall increase of £56.409m (as set out in table 2 and in Annex A). Key elements of this include:
a) New schemes funded by prudential borrowing totalling £3.353m as set out in table 3;
b) Extension of prudential borrowing funded Rolling Programme schemes totalling £25.025m as set out in table 4;
c) Extension of externally funded Rolling Programme schemes totalling £6.030m as set out in table 5;
d) New schemes funded by external grants totalling £3.844m as set out in table 5;
e) An increase in HRA funded schemes totalling £18.157m funded from a combination HRA balances/capital receipts as set out in table 6;
ii. That Council note the total increase in Council borrowing as a result of new schemes being recommended for approval is £28.378m the details of which are considered within this report and the financial strategy report;
iii. That Council approve the full restated programme as summarised in Annex B totalling £395.186m covering financial years 2024/25 to 2028/29 as set out in table 12 and Annex B.
Reason: To ensure the Council finances its captial programme.