Issue - decisions

2010/11 Capital Programme Monitor 2

16/11/2010 - Capital Programme - Monitor 2

RESOLVED: (i)         That the 2010/11 revised budget of £73.306m, as set out in paragraph 6 of the report and Table 2, be noted.

 

                        (ii)        That the re-stated capital programme for 2010/11-2014/15, as set out in paragraph 43, Table 12 and detailed in Annex A, be noted.

 

                        (iii)       That the switching of capital receipts funding of £27k from Derwent MUGA, for use on the Huntington School TCF scheme, be approved.

 

REASON:      To enable the effective management and monitoring of the Council’s capital programme.


 

Feedback
Back to the top of the page