Decision details

Bus Corridor Works on A59 Boroughbridge Road and B1363 Wigginton Road

Decision Maker: Decision Session - Executive Member for City Strategy

Decision status: Decision Made

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

Purpose of report: The timescale is tight and the detailed design will probably start in late April or early May. Ongoing consultation is continuing with Ward Committees but the main consultation on detailed proposals will follow on in June/July, subject to the consultation approach set out in the report is approved. A report giving details of the proposed works should be available in September 2010. The final results will become evident during the construction period which should be May 2011 through to April 2012.

Members are asked to: Note the anticipated timescales for different aspect of work. Seek approvals to the approach to consultation. Note that further detailed reporting will be required on the bus corridor works affecting public highways.

Decision:

RESOLVED:          That the Executive Member for City Strategy agrees to:

 

(i)                 The consultation proposals as set out in paragraphs 12 to 14 of the report;

 

(ii)               The timescale for producing detailed reports to this Decision Session in September 2010 for further consideration; detailed in paragraph 9 of the report.

 

REASON:                  To ensure that the Access York Phase 1 project continues to progress satisfactorily and to make sure that any approval of works within the public highway receives appropriate consultation

Publication date: 12/05/2010

Date of decision: 11/05/2010

Decided at meeting: 11/05/2010 - Decision Session - Executive Member for City Strategy

Effective from: 14/05/2010

Accompanying Documents:

 

Feedback