Purpose of report: The
timescale is tight and the detailed design will probably start in
late April or early May. Ongoing consultation is continuing with
Ward Committees but the main consultation on detailed proposals
will follow on in June/July, subject to the consultation approach
set out in the report is approved. A report giving details of the
proposed works should be available in September 2010. The final
results will become evident during the construction period which
should be May 2011 through to April 2012.
Members are asked to: Note the anticipated timescales for different
aspect of work. Seek approvals to the approach to consultation.
Note that further detailed reporting will be required on the bus
corridor works affecting public highways.
Decision:
RESOLVED: That the Executive Member for City Strategy agrees to:
(i) The consultation proposals as set out in paragraphs 12 to 14 of the report;
(ii) The timescale for producing detailed reports to this Decision Session in September 2010 for further consideration; detailed in paragraph 9 of the report.
REASON: To ensure that the Access York Phase 1 project continues to progress satisfactorily and to make sure that any approval of works within the public highway receives appropriate consultation
Publication date: 12/05/2010
Date of decision: 11/05/2010
Decided at meeting: 11/05/2010 - Decision Session - Executive Member for City Strategy
Effective from: 14/05/2010