Decision details

2009/10 City Strategy Capital Programme Budget Report

Decision Maker: Executive - for meetings from 03/06/00 to 26/04/11

Decision status: Item Called In

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

Purpose of report: Report sets out the proposed 2009/10 programme of works to be delivered using the City Strategy Capital Programme budget.

Members are asked to: Approve the inclusion of additional funding into the 2009/10 Capital Programme. Approve the list of schemes to be delivered in 2009/10.

Decision:

RESOLVED: (i)         That the base 2009/10 City Strategy Transport Capital Programme be approved as set out below, subject to the addition of the cycling schemes agreed under the previous item (Minute 212 refers).

 

Type

Scheme

09/10 Cost K

Location

1.      Access York Phase 1

New Access York Phase 1 CYC Study

1,047.00

Dringhouses Rural West and Rawcliffe

  1. Outer Ring Road

Hopgrove Roundabout

300.00

Huntington

  1. Outer Ring Road

Access York Phase 2 RFA top up

200.00

Rawcliffe

  1. Multi-Modal Schemes

Fulford Road Multi-Modal Scheme

600.00

Fulford Fishergate

  1. Multi-Modal Schemes

Blossom Street Multi-Modal Scheme

500.00

Micklegate

  1. Multi-Modal Schemes

Fishergate Gyratory Multi-Modal Scheme

150.00

Fishergate Guildhall

  1. Air Quality, Congestion & Traffic Management

New Urban Traffic Management and Control (UTMC)

100.00

All

  1. Air Quality, Congestion & Traffic Management

Purchase of Air Quality monitoring equipment

30.00

All

  1. Park & Ride

New P&R Site Upgrades Scheme

25.00

Several

  1. Park & Ride

New P&R City Centre Bus Stop Upgrades

25.00

Micklegate Guildhall

  1. Public Transport Improvements

Haxby Station Study Work to develop Major Scheme Bid for new station (not included in base budget) RFA top up

250.00

Haxby

  1. Public Transport Improvements

New Bus Location and Information Sub-System (BLISS) Scheme Ongoing programme of improvements

100.00

All

  1. Public Transport Improvements

New Bus Stop & Shelter Programme Scheme Ongoing programme of improvements

50.00

Several

  1. Public Transport Improvements

A59/Beckfield Lane Junction Improvements Scheme Completion of 2008/09 scheme

25.00

Acomb

  1. Public Transport Improvements

New Dial & Ride Vehicle Scheme Purchase of new vehicle for Dial & Ride service

80.00

Several

  1. Walking

Haxby Village Pedestrian Audit (Phase 2) Scheme Programme of upgrades to high priority routes to services

50.00

Haxby

  1. Walking

New Minor Pedestrian Schemes Budget Scheme Provision of minor improvements to network throughout the year

40.00

All

  1. Walking

New Dropped Crossing Budget Scheme Provision of dropped kerbs at locations requested by residents

35.00

All

  1. Walking

New Pedestrian Scheme Development Study Development of future years schemes

10.00

All

  1. Cycling

New Lendal Hub Station Scheme New secure cycle parking facility

270.00

Micklegate

  1. Cycling

Cycle margin and track surface upgrades

54.00

Several

  1. Cycling

Other Cycling City Schemes Scheme Implementation of Cycling City programme

211.00

Several

  1. Cycling

New Crichton Avenue Scheme Kingsway North to Wigginton Road

575.00

Clifton

  1. Cycling

Wigginton Road (Hospital) Scheme Development of scheme at northern end of route

100.00

Clifton

  1. Cycling

New Bootham Crossing Scheme Implementation of new crossing at southern end of Hospital Grounds route

75.00

Clifton Guildhall

  1. Cycling

New Access to Station Study Feasibility work on link from Post Office Lane to station

10.00

Micklegate

  1. Cycling

New Cycle Minor Schemes Scheme Allocation to undertake minor works throughout the year

25.00

Several

  1. Cycling

New Cycling Scheme Development Study Development of future years schemes

20.00

Several

  1. Development- Linked Schemes

Barbican to St George's Field Route Scheme Implementation of works to improve pedestrian facilities

125.00

Fishergate

  1. Development- Linked Schemes

Approaches to Hungate Bridge  Study Link to Navigation Road New James St Link Road Phase 2 Study

10.00

Heworth

  1. Safety Schemes

New Local Safety Schemes Implementation of safety schemes at casualty cluster sites

74.00

Several

  1. Safety Schemes

New Speed Management Schemes Implementation of schemes to address speeding issues

75.00

Several

  1. Safety Schemes

New Danger Reduction Schemes Improvements at sites where there is a perceived danger issue

50.00

Several

  1. Safety Schemes

New Safe Routes for 'Playbuilder' Schemes Study/ Schemes Study (and potential implementation) of safe routes to new 'Playbuilder' sites

50.00

Several

  1. School Schemes

- Safe Routes to School Schemes to be confirmed

200.00

Several

  1. School Schemes

- School Cycle Parking Schemes  to be confirmed

50.00

Several

  1. Safety Schemes

New Village Accessibility Review Study Review of junctions to produce priority list of schemes

25.00

Several

  1. Village accessibility review  implementation

Mill Lane/Wigginton Road, Dunnington/Common Lane/A1079, Deighton/A19, Towthorpe/Strensall Road and A64 junctions east of York (e.g. Hazelbush).

250.00

Haxby, Derwent, Wheldrake, Strensall

 

Total Integrated Transport Programme

6,042.00

 

 

Total Integrated Transport Overprogramming

990.00

 

 

Total Integrated Transport Budget

5,052.00

 

 

Plus RFA supplement (over 2 years)

£2.777 million

 

 

REASON:      To implement the Council’s transport strategy, as identified in York’s second Local Transport Plan (LTP).

 

                        (ii)        That Option 1 (Outer Ring Road congestion reduction improvement) be approved as the preferred use of the supplementary LTP allocation provided by the Regional Transport Board.

 

REASON:      To ensure the additional funding is used to deliver significant improvements to the City’s transport system and to meet LTP and LAA targets.

 

                        (iii)       That Officers be requested to undertake such accident analysis and preliminary design work as may be necessary to establish the relative costs / benefits of the schemes listed in paragraphs 37 and 41 of the report (improved pedestrian / cycle access to the railway station and improvements to the transport network for local communities), with a view to implementing these schemes as early in the capital programme as resources allow.

 

REASON:      To ensure that the delivery of these schemes is prioritised.

Publication date: 31/03/2009

Date of decision: 31/03/2009

Decided at meeting: 31/03/2009 - Executive - for meetings from 03/06/00 to 26/04/11

Issue status: The decision is currently being reconsidered

Accompanying Documents:

 

Feedback
Back to the top of the page