Decision details
SAR Traffic Signal Refurbishment – Junction of Fossbank/Foss Islands Road/Layerthorpe/Peasholme Green
Decision Maker: Director of City Development
Decision status: Decision Made
Is Key decision?: No
Is subject to call in?: No
Decision:
Background
The project was initiated in 2022 and is focused on renewal of the
existing traffic signal control infrastructure as the junction is
currently the worst condition traffic signal site amongst CYC
assets and is 27 years old.
The project is currently intended for delivery in early 2026 with
an anticipated cost of £165k.
Preliminary designs for alternative refurbishment options including
reallocation of existing carriageway space to Active Travel modes
were compiled and subject to transport modelling and review by CYC
officers but were not recommended for delivery at this time due to
potential impacts on wider Local Transport Strategy aims.
Decision:
To approve works at the junction of Fossbank/Foss Islands
Road/Layerthorpe/Peasholme Green including:
• Replacement of all traffic signal equipment including,
controller, traffic signal heads, detection (AI TCams), poles and
cabling.
• Convert to an ELV / LED site
• Reuse of existing ducting work.
• Installation of NAL sockets for all traffic signal poles and
plumb into existing duct network.
• Retention of far side pedestrian crossing technology
• Reuse of existing site fibre communications link
• Reuse of existing site power supply
The reason for these works being to ensure that the junction can
continue to be operated effectively.
Options Considered:
Options Considered:
Proceed to Detailed Design and Delivery Phases for the works
outlined below.
Proposed Works
The proposed design is a standard refurbishment of the existing
traffic signal equipment at the junction. The works proposed for
the site are:
• Replace all traffic signal equipment including, controller,
traffic signal heads, detection (AI TCams), poles and
cabling.
• Convert to an ELV / LED site thus significantly reducing our
costs in terms of energy and maintenance.
• Reuse of existing duct work.
• Install NAL sockets for all traffic signal poles and plumb
into existing duct network.
• Retain far side pedestrian crossing technology
• Reuse existing site fibre communications link
• Reuse existing power supply
Taking these steps ensures the ongoing operational function of the
junction, reducing the risk of asset failure and also providing
benefits with regards reduced energy consumption of the equipment.
Works undertaken will not result in significant abortive costs as
all equipment to be installed can be reused as part of future works
at either this junction or at other signal controlled locations
across the city.
Options Rejected:
Do nothing. Rejected due to the life expired
nature of the equipment on this section of the Inner Ring Road
which is now difficult and costly to maintain and needs to be
refurbished.
Proceed with a design option which includes amendments to the
layout/civils infrastructure elements of the junction and signal
phasing arrangements. Rejected due to:
• the potential impacts of these changes on existing proposals
relating to both the Local Transport Strategy and Bus Service
Improvement Plan
• potential future revisions to the land use of the Fossbank
retail site and the resulting network capacity demands generated by
the site.
Publication date: 28/11/2025
Date of decision: 27/11/2025