Decision details
TSAR Traffic Signal Refurbishment – YK2424 Heworth Green Dodsworth Avenue
Decision Maker: Director of City Development
Decision status: Decision Made
Is Key decision?: No
Is subject to call in?: No
Decision:
The project was initiated in 2025 and is
focused on renewal of the existing traffic signal control
infrastructure as the crossing is currently among the worst
condition traffic signal sites across CYC assets.
The proposed works, alongside Stakeholder correspondence were
presented to the Executive Member for Transport and Ward
Councillors on 22/07/2026. They were supportive of the project and
agreed that it can proceed under Chief Officer Decision.
Ward Councillor and Stakeholder commentary regarding considerations
for future improvements in the vicinity of the crossing are to be
considered as part of a wider transport corridor project.
The project is currently intended for delivery in Autumn 2026 with
an anticipated cost of £200k.
Options Considered:
Proceed to Delivery Phase for the works
outlined below.
Proposed Works
The proposed design is a largely standard refurbishment of the
existing traffic signal equipment at the crossing, with resurfacing
in the vicinity of the crossing. The works proposed for the site
are:
• Refurbishment of the traffic signal equipment and ducting
networks to:
o Ensure traffic signal standards are met.
o Use LED and ELV technology traffic signals
o Include Puffin style near side red / green man displays
o Provide above ground vehicle and pedestrian detection
o Create a maintainable ducting network
o Link to communications network to ensure reliable fault
monitoring and UTC connectivity
• Review existing tactile paving and amend so they are brought
up to standard wherever possible.
• Undertake a review of the island width to see if it can be
enlarged to better meet the need of pedestrians without impacting
on carriageway users significantly.
• Review of the requirement for guardrailing on the pedestrian
island
• Relocate the traffic signal controller and provide a new
electrical supply
• Resurfacing of the approaches to the crossing.
• Review and update road marking to standard including
reviewing of on carriageway cycle lanes in the direct area of the
crossing – this is to include “floating”
zigzags.
Taking these steps ensures the ongoing operational function of the
crossing, reducing the risk of asset failure and providing benefits
with regards reduced energy consumption of the equipment.
Options Rejected:
Do nothing. Rejected due to the life-expired
nature of the equipment in this section which is now difficult and
costly to maintain and needs to be refurbished. Assets at the site
are in excess of 25 years old and would require emergency
replacement if they were to fail, incurring significant
cost.
Publication date: 23/07/2026
Date of decision: 23/07/2026