Issue - decisions
Lendal Arch Gyratory - Station Road Cycle Lane
18/12/2017 - Lendal Arch Gyratory - Station Road Cycle Lane
Assistant Director, Transport, Highways and
Environment agreed that proposals 1a, 1b, 3, 4 and 5 are discounted
based on the reasoning provided within the report. Agreed Option 2
is not forwarded as presented, however the option of claiming land
is explored as part of a separate scheme that focuses on cycle and
pedestrian facilities.
It is agreed that the layout that is progressed through the
detailed design stage is the one supported by the Principal
Designer.
A record of the reasoning behind the decision to be forwarded to
York Cycling Campaign (YCC) for their information as outlined in
the report.
The detailed design will be completed and construction will
commence as planned in January 2018.